GENERAL CONTRACTOR · BC✦INSURED✦GC · ELECTRICAL · PLUMBING✦FREE QUOTE IN 1 BUSINESS DAY✦250-891-2227✦INFO@ACAPLTD.CA✦GENERAL CONTRACTOR · BC✦INSURED✦GC · ELECTRICAL · PLUMBING✦FREE QUOTE IN 1 BUSINESS DAY✦250-891-2227✦INFO@ACAPLTD.CA✦GENERAL CONTRACTOR · BC✦INSURED✦GC · ELECTRICAL · PLUMBING✦FREE QUOTE IN 1 BUSINESS DAY✦250-891-2227✦INFO@ACAPLTD.CA✦GENERAL CONTRACTOR · BC✦INSURED✦GC · ELECTRICAL · PLUMBING✦FREE QUOTE IN 1 BUSINESS DAY✦250-891-2227✦INFO@ACAPLTD.CA✦
Request a Free Quote→250-891-2227→

Process · October 13, 2026 · 7 min read

Foundation and Framing Inspections for a New Home in Saanich and Greater Victoria

Costs, fees and rules last verified October 13, 2026

Short answer

Saanich requires inspections at each stage of a new house: excavation and footings, foundation forms, underslab radon and plumbing, slab insulation, framing and sheathing, then insulation and final. Each is booked after its work is ready but before it is covered. Book by 3 p.m. the business day before. Other municipalities use similar stages with their own rules.

On a new home, the first inspections decide whether the next trade can start. Concrete cannot be poured until the footings are approved, and walls should not be closed in until the frame is. Saanich publishes a detailed guide to its residential inspections, which makes it a good model for what happens in most Greater Victoria municipalities. This guide walks through the foundation and framing stages using that guide, and flags where your own municipality may differ.

This is general information, not code advice. Your permit package and your building department are the authority, and the Saanich guide says it is advisory only.

How inspections are booked

In Saanich you book through a MySaanich account or by phone, and you need the permit number, site address, type of inspection and requested date. Inspections must be booked before 3:00 p.m. on the business day before to be inspected the next business day. Inspection fees are included in the permit fees and cover one inspection and one re-inspection at each stage. Where non-compliant work needs more, the guide lists additional re-inspection fees starting at the third re-inspection. An inspector can also refuse an inspection if the site is unsafe or untidy, so a clean site counts.

The stages, in order

StageWhen it is bookedWhat the inspector looks at
Excavation and footingsAfter excavating and setting footing forms, before concreteUndisturbed bearing soil visible, standing water and organic material removed, footing sizes and locations matching the approved plans
Foundation formsAfter wall forms are set, before concreteForm size and layout matching approved drawings, earlier deficiencies cleared
Underslab radonAfter underslab piping and granular layer, before the sealed air barrier100 mm of gas-permeable granular layer under the slab, pipe inlet placement, continuous layer
Underslab plumbingAfter groundwork is complete and under test, before concreteFixture count and locations, piping bedded and graded, all piping under test
Slab and foundation insulationAfter insulation and air barrier are in place, before concreteAdequate insulation in conditioned spaces, a sealed below-ground air barrier, assemblies matching the energy report
Dampproofing and drainageAfter pipework, dampproofing and drain rock are done, before backfillDampproofing, separate pipes for foundation drainage and rainwater leaders, 150 mm of drain rock on top and sides of the drain pipe
Framing and sheathingSheathing after it is complete but before the membrane; framing immediately before insulationStructure, layout, fire and life safety items, ventilation, rough-ins complete, building at lock-up

The guide continues with pre-cladding, insulation, fire separation, stucco wire where it applies, and the final inspection. The details above are from the Saanich Residential Inspections Guide, updated April 22, 2025.

Footings and foundation forms: what trips people up

The guide's excavation checklist includes undisturbed bearing soil that is exposed and visible, a minimum bearing capacity of 75 kPa unless the structural drawings specify otherwise, and a minimum excavation depth of 450 mm to the underside of footings. A sealed bearing letter from a geotechnical engineer is acceptable to confirm soil capacity, and up to 50 mm of granular material can be placed over the bearing soil after the excavation is approved.

The items it lists as commonly missed at this stage are practical: bearing soil that is not visible, professionals who have not provided their field reviews, and a footing location that does not match the approved drawings. If your lot is sloped or rocky, the footing stage is where the extra cost shows up, which is covered in our guide to building on a sloped lot at Bear Mountain.

Radon rough-in is now part of the foundation

The Saanich guide says that as of March 8, 2024, all conditioned buildings regulated by the BC Building Code require a rough-in for a subfloor radon depressurization system. It is inspected in two stages. The subfloor components are inspected before they are covered, and the above-ground vent piping at or before the framing inspection. The guide also notes that road base is not approved for the gas-permeable layer.

The framing and sheathing inspection

The framing and sheathing inspection confirms general code and bylaw compliance and that the building matches the approved drawings. The guide says changes that have not been approved will fail the inspection. To book it, the framing checklist expects the building to be at lock-up (roof and windows complete), all plumbing, electrical and mechanical rough-ins complete, professionals' field reviews submitted, and the BC land surveyor's height and site surveys approved. For projects with ventilation work, a ventilation checklist must be complete and on site, or submitted before the inspection.

Timing matters. The sheathing inspection is booked after exterior sheathing is complete but before the sheathing membrane goes on, unless a professional has approved the nailing. The framing inspection must happen immediately before insulation. This is why rough-in trades and framers need one shared schedule, covered in the order of trades.

The inspection checks the building against the approved drawings, so it is the same whether the walls were framed on site or built as panels in a shop. If you are weighing prefab walls, OG Prefab explains how to line up the foundation with panel delivery, which matters because the foundation has to be approved and dimensionally checked before anything is built to it.

Other municipalities

The BC Building Code sets the technical rules, but each municipality sets its own booking process, required documents and, in some cases, extra stages. We have used Saanich here because it publishes a detailed guide. Langford, Colwood, Victoria and the CRD each have their own pages and permit conditions, so confirm yours before you plan the schedule. How long the permit itself takes is covered in building permit timelines in Greater Victoria.

What a general contractor does around inspections

A contractor does not make inspections faster, but it can make sure each one is booked when the work is ready, the field reviews and surveys are in hand, and deficiencies from the last stage are closed out before the next one. That is part of ACAP LTD's general contracting service.

See where inspections fall in your build with the free timeline planner - pick your municipality and project type to map the phases.

Planning a new build and want the inspection schedule built into the plan? Get in touch with ACAP LTD.

Build and Renovation Timeline Planner - See a phase-by-phase timeline for your build or renovation, from permit to final inspection.

Frequently asked questions

How much notice do I need to book an inspection in Saanich?

Saanich says inspections must be booked before 3:00 p.m. on the business day before the required inspection to be inspected the next business day. You book through a MySaanich account or by phone, with the permit number, site address, inspection type and requested date.

What does an inspection cost if it fails?

Saanich says inspection fees are included in the permit fees and cover one inspection and one re-inspection at each stage. Its 2025 guide lists additional non-refundable re-inspection fees from the third re-inspection: $100, $200, $500 and $400 for the sixth or greater. Check the current bylaw before relying on these amounts.

Can concrete be poured before the footing inspection?

No. The Saanich guide says the excavation and footings inspection happens after excavating and setting footing forms but before placing concrete, and foundation forms are inspected after the wall forms are set but before concrete.

Does a new house need a radon rough-in?

In Saanich's guide, as of March 8, 2024, all conditioned buildings regulated by the BC Building Code require a rough-in for a subfloor radon depressurization system. It is inspected in two stages: subfloor components before they are covered, and the above-ground vent piping at or before the framing inspection.

Do other Greater Victoria municipalities inspect the same stages?

The BC Building Code sets the technical rules, but each municipality publishes its own booking process, documents and stage list. Saanich is used here because it publishes a detailed guide. Check your own municipality's requirements, and use your permit package as the authority.